P63.10-4854-08
1 Cut out spot welds on rear shelf (4) (areas K, M and N).
Spot welds in area N must be cut out from inside.
2 Cut out spot welds on connecting panel (5) (area L).
3 Remove connecting panel (5) from rear shelf (4).
P63.10-4857-08
4 Grind mating surfaces on inner C-pillar (1) down to bare metal in crosshatched areas.
Grind spot weld flanges down to bare metal on both sides.
5 Coat insides of spot welding flange on inner C-pillar (1) with zinc dust paint.
To prevent adhesion problems, do not coat bonding surfaces with zinc dust paint (areas L1, L2 and L3).
Observe pretreatment of bonding surfaces (areas L1, L2 and L3).
P63.10-4860-07
6 Scribe separation points on outer C-pillar (2) and reinforcement (3) (areas O and P).
Take separation points from vehicle
7 Cut outer C-pillar (2) and reinforcement (3) at separation points (areas O and P).
8 Remove sections from outer C-pillar (2) and reinforcement (3).
9 Grind mating surfaces on inner C-pillar (1), outer C-pillar (2) and reinforcement (3) down to bare metal in crosshatched areas.
Grind spot weld flanges down to bare metal on both sides.
10 Coat insides of spot weld flange on inner C-pillar (1), outer C-pillar (2) and reinforcement (3) with zinc dust paint.
To prevent adhesion problems, do not coat bonding surfaces with zinc dust paint (areas F1, L4 and L5).
Observe pretreatment of bonding surfaces (area F1, L4 and L5).