P32.22-2552-09
Shown on MODEL 222.082 without pressure reservoir |
10 | Right front suspension strut | 13 | Left rear suspension strut | Y36/6 | AIRMATIC valve unit | ||
11 | Left front suspension strut | A9/1 | AIRMATIC compressor | ||||
12 | Right rear suspension strut | N51/3 | AIRMATIC control unit |
Shown on vehicle with pressure reservoir |
A | Pressure reservoir |
P32.22-2516-05
Shown on MODEL 222.082 |
A9/1 | AIRMATIC compressor |
A9/1y1 | AIRMATIC pressure reduction valve |
Y36/6 | AIRMATIC valve unit |
Y36/6b1 | AIRMATIC pressure sensor |
Y36/6y1 | Left front level control valve |
Y36/6y2 | Right front level control valve |
Y36/6y3 | Left rear level control valve |
Y36/6y4 | Right rear level valve |
Y36/6y5 | AIRMATIC central reservoir filling valve |
P32.31-2088-06
| Notes on AIRmatic | ||
| Remove/install | ||
1 | Remove front engine compartment paneling | ||
2 | Remove left front fender liner | ||
3 | Expose pressure line connections on rear suspension struts (12, 13) |
| |
Model 217 | |||
| Check | ||
4 | Spray pressure line connections on suspension struts (10, 11, 12,13) with leak detection spray | Wait for roughly 10 to 15 minutes after spraying the compressed-air lines. This allows smaller leaks to be detected (bubbles form). Larger leaks are visible immediately. | |
Leak detection spray | |||
5 | Spray top and bottom of dust boots on suspension struts (10, 11, 12, 13) with leak detection spray | After spraying the top and bottom of the dust boots on the suspension struts, wait approx. 10 to 15 min. This allows smaller leaks to be detected (bubbles form). Larger leaks are visible immediately. | |
Leak detection spray | |||
6 | Spray leak detection spray onto the pressure line connections on AIRmatic valve unit (Y36/6) and AIRMATIC compressor (A9/1) | Wait for roughly 10 to 15 minutes after spraying the compressed-air lines. This allows smaller leaks to be detected (bubbles form). Larger leaks are visible immediately. | |
Leak detection spray | |||
7 | Spray leak detection spray onto the pressure line connections on the pressure reservoir (A) (if installed) | Wait for roughly 10 to 15 minutes after spraying the compressed-air lines. This allows smaller leaks to be detected (bubbles form). Larger leaks are visible immediately. | |
Leak detection spray | |||
8 | Cover rear shelf or trim in area of pressure line connections with clean rags | Socket wrench bit | |
Knife | |||
If pressure line connections are defective | |||
| |||
Repair AIRmatic pressure line connection | |||
9 | Install in the reverse order |
000 589 12 28 00
Knife
211 589 00 09 00
Socket wrench bit
Henviste dokumenter
- ah3222p100002lf Oplysninger om AIRmatic
- ar3222p200102sx
- ar3225p1016lfb
- ar3225p1016lfs
- ar6120p1105lf
- ar8810p1300lf