gf9800t3100a

Paintwork/corrosion protection Istanbul plant

ประเภท gf · หัวข้อ 98.00 · เวอร์ชัน 0100 · 2000-01-12

ใช้กับ: MODEL 613, 671

ไม่มีใน “th” แสดงเป็น อังกฤษ

ตำแหน่ง

กลุ่มฟังก์ชัน 3 Body › 98 Paintwork › 98.00 General — ซีรีส์ 613 · ซีรีส์ 671

GF98.00-T-3100A

Paintwork/corrosion protection Istanbul plant

22.6.99

MODEL 613, 671

The Istanbul plant is one of the most modern bus plants in Europe producing the following bus models

O 403

O 345 and

O 345 G.

Outside of Turkey, the sales designation O 350 is used for the
O 403.

The following illustration shows the corrosion protection measures performed at the Istanbul plant beginning with cleaning the unfinished body (skeleton), priming and painting, right up to hollow cavity preservation. The temperatures specified are based on the surface temperature of the buses.

-----------------------------------------------------------------------------------------

The following chapters and documents illustrate how reliable corrosion protection is achieved for the bus models produced in Istanbul by the use of design measures, production processes, painting procedures and use of special materials.

Steps 1 - 11 are performed in the Dauutpasa section of the plant, the actual paintwork beginning with Item 12 is completed in the Hosdere section of the plant.

-----------------------------------------------------------------------------------------

Paintwork/corrosion protection Istanbul plant

M98.00-0020-79

A Manual 1 Cleaning

2 Application of zinc dust paint

3 Coating of hollow cavities with zinc dust paint

4 Coating of roof/sides with spotwelding paste

5 Paneling and cleaning chassis

6 Application of filler, first coat

13 Sanding and cleaning body

14 Application of top coat

15 Evaporation

16 Application of clear paint (only for metallic paint)

17 Top coat drier, 80 °C, 60 min.

18 Preservation of hollow cavities

7 Filler drier, 130 °C, 30 min.

8 Filling work and seam sealing

9 Application of filler, second coat

10 Spraying underbody protection agent

11 Filler drier, 130 °C, 65 min.

12 Repair of flaws

Paintwork/corrosion protection Istanbul plant

M98.00-0021-76

Paint finish, coating thicknesses on skeleton frame

1 Primer with zinc dust paint 20 μm

2 2K thick layer filler 45 5 μm

Paint finish, coating thicknesses on paneling

Non-metallic paint

3 Sheet metal galvanized

zinc coating thickness approx. 20 μm

4 2K thick layer filler 70 110 μm

(total)

5 Top coat 45 5 μm

Metallic paint

3 - 4 same as above

5 Metallic base paint 20 5 μm

6 2K clear paint 45 5 μm

7 Structured effect paint 150 300 μm

(structured paint)

only luggage compartment, interior front end and stowage compartments

8 PVC plastisol 150 300 μm

9 Black matt paint 25 5 μm

Paintwork/corrosion protection, standard production, general

GF98.00-P-2000A