Commissioning of a new ZV /FFB control module - Central locking control
As informed by ITP 0001/20, the supply of the FFB/ZV control module has been changed.
Now, if in need to replace the control module, it will no longer be necessary to acquire new controls together with the new control module and the current customer controls can be used.
The application of a new control module is carried out via menu: FFB Activations Commissioning the new control module.
Notes on the new process:
Only the first control can be learned in the new control module without a known control already registered in the module.
From the second control it is necessary to authorize using a known control, as usual.
Additional control can be added at any time via the “Register a new transmitter” menu, as usual.
The guidelines described in the letter VPS3-0004/2020 and ITP 0001/20 must also be observed.