Test and adjustment values of torque converter
Number | Designation | Transmission | Transmission 721.151/181/182 | ||
BE27.20-N-1001-01B | Installed dimension "F" from converter flange-mounting surface to transmission flange-mounting surface | Version A | mm | 70.75 to 71.75 | 70.75 to 71.75 |
Version B | mm | 76.50 to 77.50 | 76.75 to 77.50 | ||
Version C | mm | 80.75 to 81.75 | 80.75 to 81.75 | ||
Version D | mm | 85.75 to 86.75 | 85.75 to 86.75 | ||
See picture | mm | ||||
BE27.20-N-1002-01B | Axial play, thrust bearing of torque converter | mm | 0.3 to 0.4 | 0.3 to 0.4 | |
Test and adjustment values of torque converter
Number | Designation | Transmission 721.913/914/ | ||
BE27.20-N-1001-01B | Installed dimension "F" from converter flange-mounting surface to transmission flange-mounting surface | Version A | mm | 70.75 to 71.75 |
Version B | mm | 80.75 to 81.75 | ||
Version C | mm | 85.75 to 86.75 | ||
Version D | mm | - | ||
See picture | mm | |||
BE27.20-N-1002-01B | Axial play, thrust bearing of torque converter | mm | 0.3 to 0.4 | |
T27.20-0003-01
1 Measure installed dimension 'F' from the flange surface - converter to the flange surface - transmission using a depth gauge
Carry out the measurement at several points of the circumference and calculate the mean value from various measurement results.
2 Note converter installed dimension (F).