W26.45-1357-09
1 | Housing cover | 19 | Shim | 36 | Housing | ||
2 | Cylinder pin | 20 | Spacer ring | 37 | Cover | ||
3 | Bushes | 21 | Intermediate gear | 38 | Cover | ||
4 | Tapered roller bearing | 22 | Tapered roller bearing | 39 | Ball | ||
5 | Output shaft | 23 | Intermediate shaft | 40 | Shift cylinder | ||
6 | Tapered roller bearing | 24 | Cylindrical roller bearing | 41 | Seal | ||
8 | Tapered roller bearing | 25 | Drive shaft | 42 | Slide ring | ||
9 | Cluster gear | 26 | Needle roller bearing | 43 | Piston with shift rod | ||
10 | Retaining ring | 27 | Gear | 44 | Sealing ring | ||
11 | Spacer ring | 28 | Needle roller bearing | 45 | Shift fork | ||
12 | Spacer ring | 29 | Sliding sleeve | 46 | Compression spring | ||
13 | Shim | 30 | Driver | 47 | Jack | ||
14 | Tapered roller bearing | 31 | Shim | 48 | Control plunger | ||
15 | Intermediate shaft | 32 | Ball bearing/cylindrical roller bearing | 49 | O-rings | ||
16 | Tapered roller bearing | 33 | Centering ring | 57 | Shim | ||
17 | Shim | 34 | Shim (only with PTO 125-10b) | S2 | Power take-off 1 indicator switch | ||
18 | Retaining ring | 35 | Retaining ring |
Shown with power take-off 125-10b |
6 | Tapered roller bearing |
34 | Shim (with PTO 125-10b) |
36 | Housing |
52 | Seal (only PTO 125-10b or 125-11b) |
53 | Flange (only PTO 125-10b or 125-11b) |
54 | Radial shaft sealing ring (only PTO 125-10b or 125-11b) |
55 | Output flange (only PTO 125-10b or 125-11b) |
56 | Washer (only PTO 125-10b or 125-11b) |
57 | Shim (only PTO 125-10b or 125-11b) |
58 | Screw plug |
59 | Screw plug |
60 | Drain screw |
61 | Oil pipe |
62 | Oil pipe |
63 | Oil pipe |
64 | Stud bolt |
65 | Core hole cover |
66 | Housing cover (with PTO 125-10b) |
67 | Seal (with PTO 125-10b) |
W26.45-1358-06
Shown with power take-off 125-11b |
6 | Tapered roller bearing |
36 | Housing |
52 | Seal (only PTO 125-10b or 125-11b) |
53 | Flange (only PTO 125-10b or 125-11b) |
54 | Radial shaft sealing ring (only PTO 125-10b or 125-11b) |
55 | Output flange (only PTO 125-10b or 125-11b) |
56 | Washer (only PTO 125-10b or 125-11b) |
57 | Shim (only PTO 125-10b or 125-11b) |
58 | Screw plug |
59 | Screw plug |
60 | Drain screw |
61 | Oil pipe |
62 | Oil pipe |
63 | Oil pipe |
64 | Stud bolt |
65 | Core hole cover |
W26.45-1360-06
Shown with power take-off 125-11c |
6 | Tapered roller bearing |
36 | Housing |
50 | Seal (only PTO 125-11c) |
51 | Flange (only PTO 125-11c) |
57 | Shim |
58 | Screw plug |
59 | Screw plug |
60 | Drain screw |
61 | Oil pipe |
62 | Oil pipe |
63 | Oil pipe |
64 | Stud bolt |
65 | Core hole cover |
W26.45-1359-06
Warning | Risk of injury. Skin or eye injuries may result when handling hot or glowing objects. | Wear protective gloves, protective clothing and safety glasses, if necessary. | |
Topical note | Notes on self-locking nuts and bolts | ||
| Assemble | ||
1 | Coat ends of oil pipes (61, 62, 63) with lubricant and install oil pipes (61, 62, 63) into housing (36). | ||
Coat core hole cover (65) and stud bolt (64) with thread locking compound. | |||
Screw plug to housing | |||
Synthetic grease 50 g | |||
Quick-acting adhesive, Loctite 270 | |||
2 | Drive cylindrical roller bearing (24) into housing cover (1) using a suitable drift. | ||
3 | Install ball bearing/cylindrical roller bearing (32) into housing (36) using a suitable drift. | ||
4 | Clean sealing surfaces on housing (36) and housing cover (1). | | |
5 | Install shift cylinder (40). | ||
6 | Assemble drive shaft (25). |
| |
Drive shaft with cylindrical roller bearing | |||
Axial play of bearing on drive shaft | |||
7 | Install drive shaft (25) with shift fork (45) and control plunger (48). | Replace O-rings (49) on control plunger (48) and coat with lubricant. | |
Synthetic grease 50 g | |||
8 | Install compression spring (46). | ||
9 | Assemble and adjust intermediate gear (21). | ||
Axial play of bearing on intermediate shaft | |||
10 | Install intermediate gear (21) with intermediate shaft (23). | Align groove in intermediate shaft (23) with housing cover (1). | |
11 | Assemble output shaft (5). | ||
Screw/nut, housing cover to housing | |||
Axial play of output shaft bearing in housing | |||
Synthetic grease 50 g | |||
12 | Install output shaft (5). | ||
13 | Assemble cluster gear (9). | ||
Axial play of bearing on intermediate shaft | |||
14 | Install cluster gear (9) with intermediate shaft (15). | Align groove in intermediate shaft (15) relative to housing cover (1). | |
15 | Coat sealing surfaces on housing (36) with sealant. | Loctite 5203 sealant | |
16 | Attach housing cover (1) to housing (36). | Observe installation position of cylindrical pins (2). When replacing the housing cover (1) replace the parallel pins (2) and bushes (3). | |
Screw/nut, housing cover to housing | |||
17 | Insert balls (39). | ||
18 | Insert both caps (37, 38) of intermediate shafts (23, 15) with sealant and install. | Replace bolts. | |
Bolt to intermediate shaft | |||
Loctite 5203 sealant | |||
19 | Screw in screw plugs (58, 59) with new sealing rings. | Screw plug to housing | |
20 | Determine shim (34) of drive shaft (25). | Only if power take-off 125-10b is installed. | |
Axial play of drive shaft bearing in housing | |||
Strip clamp | |||
21 | Install tapered roller bearing (6) using a suitable drift. | ||
22 | Determine shim (57) of output shaft. | ||
Axial play of output shaft bearing in housing | |||
Strip clamp | |||
23 | Install radial shaft sealing ring (54) into flange (53) using a suitable drift. | Only if power take-off 125-10b or 125-11b is installed. | |
Coat sealing lip of radial shaft sealing ring (54) with lubricant. | |||
Synthetic grease 50 g | |||
24.1 | Install flange (53) with shim (57) and new seal (52). | With power take-off 125-10b or 125-11b | |
Screw/nut, housing cover to housing | |||
24.2 | Install flange (51) with shim (57) and seal (50). | With power take-off 125-10c | |
25 | Install output flange (55). | Only if power take-off 125-10b or 125-11b is installed. | |
Bolt, output flange to output shaft | |||
Retainer wrench | |||
26 | Install circlip (35) on the drive shaft (25). | ||
27 | Install centering ring (33) all the way using a suitable drift. | ||
28 | Install housing cover (66) with shim (34) and new seal (67). | Only if power take-off 125-10 is installed. | |
Bolt to housing cover | |||
29 | Tightly screw in power take-off 1 indicator switch (S2) with new sealing ring. | Indicator switch to shift housing |
000 589 59 63 00
Strip clamp
717 589 00 31 00
Retainer wrench
Odkazované dokumenty
- ah0000n000101a Upozornění k samopojistným šroubům a maticím
- ar2645g0007adc
- ar2645w000503c Rozebrání, smontování hnacího hřídele pomocného pohonu
- ar2645w000503ca Rozebrání, smontování hnacího hřídele pomocného pohonu
- ar2645w000504c Rozebrání, smontování hnaného hřídele pomocného pohonu
- ar2645w000505c Demontáž, montáž olejového potrubí u skříně pomocného pohonu
- ar2645w001013c Rozebrání, smontování dvojitého kola
- ar2645w001505c Určení vymezovací podložky hnacího hřídele
- ar2645w001506c Určení vymezovací podložky hnaného hřídele
- ar2645w001603c Rozebrání, smontování, seřízení vloženého kola
- as0000z000201a Nebezpečí poranění kůže nebo očí při zacházení s horkými nebo žhavými předměty