ar0703p1010gd

Remove/install rail

Typ ar · téma 07.03 · verze 0100 · 2009-01-15

Platí pro: ENGINES 668.940 /941 /942 in MODEL 168

Není k dispozici v jazyce „cs“; zobrazeno v jazyce Angličtina.

Zařazení

Funkční skupina 1 Motor › 07 Příprava směsi › 07.03 Vstřikovací trysky, vstřikovací ventily, vedení — Řada 168 · Řada 668 (modely 940, 941, 942)

EinPAS 15 Motor › 15.45 Management motoru › 15.45.42 Rozdělovač paliva / rail / tryska / vstřikovač — Řada 168 · Řada 668 (modely 940, 941, 942)

AR07.03-P-1010GD

Remove/install rail

7.1.09

ENGINES 668.940 /941 /942 in MODEL 168

Remove/install rail

P07.16-0298-06

1 Plug connection of rail pressure sensor

2 Plug connection of pressure regulator valve

3 Bracket of pressure line

4 Torx bolts

5 Banjo bolt

6 Sealing ring

19/1 Pressure line of
high pressure pump-rail

21 Rail

21/3 Leak oil line

21/4 Fuel return line

(rail-high pressure pump)

21/6 Injection lines

22 Fuel return line

23 Sealing rings

B4/6 Rail pressure sensor

Y74 Pressure control valve

Remove/install

1

Remove induction module

AR09.20-P-1400GD

2

Separate cable ties at the rail (21)

Installation: Replace cable ties.

3

Separate plug connection of rail pressure sensor (1) and plug connection of pressure regulator valve (2)

Danger!

Risk of explosion caused by ignition of flammable products, risk of poisoning caused by inhaling fuel vapors or swallowing fuel as well as risk of injury to skin and eyes exposed to fuel.

No fire, sparks, open flames or smoking.
Pour fuels only into suitable and appropriately marked containers.

Wear protective clothing when handling fuel.

AS47.00-Z-0001-01A

4

Remove injection lines (21/6)

When slackening and tightening the union nut, counterhold at threaded connection with wrench.
On no account exceed the tightening torque in order to avoid also slackening the threaded connection the next time.

Do not pinch or bend injection lines.
After detaching the injection lines, seal connections at the injection lines. Ensure scrupulous cleanliness!

AR07.16-P-1080GD

Installation: Ensure exact seating of the injection lines. Inspect sealing cone at the lines, replace line if compression points exist.

5

Detach pressure line of high pressure pump (19/1) at rail (21)

Detach bracket (3) of pressure line

*BA07.16-P-1005-01B

6

Disconnect fuel return flow line (21/4) at the rail (21)

Pay attention to use of locking arm.

AR47.25-P-1000-01A

Installation: Replace sealing ring (6)

7

Detach fuel return flow line (22) at rail (21), pull off leak oil line (21/3)

Installation: Replace sealing rings (23)

*BA07.16-P-1007-01B

8

Remove rail (21)

If the rail is replaced:

Rail is supplied with rail pressure sensor (B4/6) and pressure regulator valve (Y74) installed

*BA07.16-P-1006-01B

9

Install in the reverse order

10

Read out fault memory and erase

Stored faults which may be caused by disconnecting cables or by simulation during removal and installation or test operations, must be processed in the fault memories after completing the work. Refer to:

Diagnosis manual for diesel engine, Volume 1.2

Common rail diesel injection (CDI)

Number

Designation

Engine 668.940/
941/942

BA07.16-P-1005-01B

Union nut, pressure line to high-pressure pump/rail/injector

Nm

23

BA07.16-P-1006-01B

Bolt, rail to cylinder head cover

Nm

9

BA07.16-P-1007-01B

Banjo bolt, leak oil line to rail

Nm

20

Odkazované dokumenty