The superordinate service document as well as the safety information in the service document must be observed.
N65.10-A013-08
1 | Install and fit front section of the roof paneling (1). |
2 | Remove roof paneling section (1). |
3 | Apply lining adhesive in the cross-hatched areas to the body (areas I). |
Observe pretreatment of bonding surfaces and manufacturer's specifications for drying and processing time of adhesive. |
4 | Apply 2-component adhesive to crosshatched area to the body (area H). |
Observe pretreatment of bonding surfaces and manufacturer's specifications for drying and processing time of adhesive. |
N65.10-A015-08
5 | Install roof paneling front section (1), fit and fix in place. |
6 | Front section of the roof paneling (1) with rivets with a diameter of 6.414 (area K). |
7 | Front section of the roof paneling (1) (areas J). |
8 | Clean weld joints. |
9 | Remove shavings. |