gf7720p3003gh

Desynchronizing sliding /pop-up roof, function

Type gf · topic 77.20 · version 0102 · 1999-10-22

Applies to: MODEL 163 with CODE (414a) Electric glass sliding/pop-up roof

Where it sits

Function group 3 Body › 77 Sliding roof, soft top, top attachments › 77.20 Electric sliding roof — Series 163

GF77.20-P-3003GH

Desynchronizing sliding /pop-up roof, function

19.2.97

MODEL 163 with CODE (414a) Electric glass sliding/pop-up roof

Definition
Desynchronization cancels synchronization of the sliding /pop-up roof, i.e. the counter status for the position measurement is no longer valid.

Function
Desynchronization is accomplished when

the sliding /pop-up roof (M12) is disconnected from the power supply (e.g. by disconnecting the battery or defective fuse), or

a malfunction has been recognized in the position measurement or

the sliding /pop-up roof has been moved with the crank (mechanical emergency actuation).

In such cases the interrelationship between the counter status in the position measurement and the actual position of the
sliding /pop-up roof is no longer true. For this reason synchroniza-tion is necessary.
In the desynchronized state only limited operation of the
sliding /pop-up roof is possible; it is only possible to open the
pop-up roof for synchronization.

Synchronizing sliding/pop-up roof, function

GF77.20-P-3002GH

Sliding/pop-up roof position measurement, function

GF77.20-P-3001GH

Convenience control

GF72.29-P-2002GH

All-activity module, location/purpose/ design/function

up to 11.99

GF54.21-P-4100GH

Extended-activity module, location/ purpose/design/function

as of 12.99

GF54.21-P-4107GK

Referenced documents