ar6320p135103src

Prepare connection points on B-pillar reinforcement

Type ar · topic 63.20 · version 0100 · 2016-02-01

Applies to: Model 453.4

Where it sits

Function group 3 Body › 63 Side wall › 63.20 Pillars — Series 453 (models 4**)

EinPAS 35 Body/frame/detachable parts › 35.34 Sidewall › 35.34.45 column — Series 453 (models 4**)

AR63.20-P-1351-03SRC

Prepare connection points on B-pillar reinforcement

Model

453.4

Prepare connection points on B-pillar reinforcement

1

Grind mating surfaces on B-pillar reinforcement (1) down to bare metal in crosshatched areas.


Sand down spot weld flanges to bare metal on both sides.



2

Remove grinding dust.



3

Coat insides of spot weld flanges with zinc dust paint.


P63.20-8797-03