Model | 447.601 |
with code T19 (Sliding door left) | |
with code W29 (Window fixed behind) | |
Left side of vehicle | |
Model | 447.601 |
with code W29 (Window fixed behind) | |
Right side of vehicle | |
Model | 447.701 |
with code T19 (Sliding door left) | |
with code W29 (Window fixed behind) | |
with code ZK4 (Mixto) | |
Left side of vehicle | |
Model | 447.701 |
with code W29 (Window fixed behind) | |
with code ZK4 (Mixto) | |
Right side of vehicle | |
Model | 447.811 |
Right side of vehicle | |
Model | 447.811 |
with code T19 (Sliding door left) | |
Left side of vehicle |
The following steps are shown on the left side of the vehicle and must be accomplished analogously on the right side in the event of damage.
S63.10-5709-09
1 | Mark separating point on side wall paneling (1) and cut (area A). |
Transfer separation point from vehicle. |
2 | Grind mating surfaces on side wall paneling section (2) down to bare metal in crosshatched areas. |
Sand down spot weld flanges to bare metal on both sides. |
3 | Remove shavings and drill chips. |
4 | Coat insides of spot weld flanges with zinc dust paint. |
Do not coat bonding surface with zinc dust paint (area B). |
Observe pretreatment of bonding surfaces (area B). |
S63.10-5710-09
5 | Grind mating surfaces on side wall paneling section (2) down to bare metal in crosshatched areas. |
Sand down spot weld flanges to bare metal on both sides. |
6 | Remove shavings and drill chips. |
7 | Coat insides of spot weld flanges with zinc dust paint. |
Do not coat bonding surface with zinc dust paint (area B). |
Observe pretreatment of bonding surfaces (area B). |
S63.10-5711-09
8 | Grind mating surfaces at lock striker reinforcement (3) and reinforcement (4) down to bare metal in crosshatched areas. |
Sand down spot weld flanges to bare metal on both sides. |
9 | Remove shavings and drill chips. |
10 | Coat insides of spot weld flanges with zinc dust paint. |
Do not coat bonding surface (area D) with zinc dust paint. |
Observe pretreatment of bonding surface (area D). |
11 | Apply sealant to reinforcement (4). |
12 | Apply 2-component adhesive to reinforcement (4) (area D). |
Observe pretreatment of bonding surface (area D). Refer to the manufacturer's information for the curing and working times of 2-component adhesive. |
13 | Install lock striker reinforcement (3) and reinforcement (4) in side wall paneling section (2), fit and fix in place. |
14 | Lock striker reinforcement (3) and reinforcement (4) (areas E and F). |
15 | Clean weld joints. |
16 | Remove shavings and drill chips. |
17 | Coat insides of spot weld flanges with zinc dust paint (area F).. |