Engine mounts, engine supports
Number | Designation | Engine 272.9 | ||
BA22.10-N-1001-01S | Bolt, front engine mount to front axle carrier | Nm | 58 | |
Automatic transmission complete
Number | Designation | Transmission 722.683/684/ | ||
BA27.10-N-1003-04B | Bolt connecting transmission housing to engine | Nm | 38 | |
Support plate
906 589 01 62 00
D01.10-1147-06
Removing
1 Remove bolts (2) of the engine mounts.
2 Place suitable wooden blocks on the transmission plate of the transmission jack (3).
Transmission jack, transmission plate for passenger cars
http://gotis.aftersales.mercedes-benz.com
3 Mount the transmission jack (3) with the transmission plate at the oil pan bottom section and lift the engine (1) until the engine mounts no longer touch the front axle carrier.
D01.10-1149-11
4 Place a suitable wooden block (6) between the transmission (5) and the engine crossmember (7) from below.
5 Lower the engine until the transmission (5) rests on the wooden block (6).
D01.10-1148-11
6 Remove bolts (4) securing transmission (5).
Do not unscrew bolts (13).
D01.10-1150-06
7 Lower the vehicle and mount a mobile workshop crane with an engine removal fixture (9) and support plate (8) at the lifting eyes of the engine (1).
Mobile workshop crane, engine removal fixture
http://gotis.aftersales.mercedes-benz.com
8 Remove bolts (13) of the transmission (5).
9 Pull off the engine (1) from the transmission (5) and lift it out.
Lift out the engine (1) carefully so that the surrounding components are not damaged.
D01.10-1151-05
Install
10 Clean the guide (10) on the torque converter (11) and the mount (12) in the crankshaft.
D01.10-1150-06
11 Position the engine (1) on the transmission (5), align the fitting sleeves of the engine (1) with the respective bolt holes on the transmission (5) and screw in the bolts (13).
Lift in the engine (1) carefully so that the surrounding components are not damaged.
Observe tightening torque.
D01.10-1149-11
12 Lift the engine with the mobile workshop crane and remove the wooden block (6) between the transmission (5) and the engine crossmember (7).
13 Lower the engine with a mobile workshop crane until it rests on the engine mounts.
Ensure that the engine mounts are seated correctly.
14 Detach the mobile workshop crane with the engine removal fixture and support plate at the engine.
15 Raise vehicle.
D01.10-1148-11
16 Screw in bolts (4) of the transmission (5).
Observe tightening torque.
17 Screw on engine mount bolts
Observe tightening torque.