A | Holes |
B | Holes |
S60.30-0197-05
1 | Tie-down rail |
2 | Tie-down rail |
S60.30-0273-06
1 | Tie-down rail |
2 | Tie-down rail |
S60.30-A062-11
S60.30-A061-08
3 | Platform paneling | 7 | Tie-down rail | |
4 | Warning | b | Dimension (approx. 200 mm) | |
5 | Warning | c | Dimension (approx. 200 mm) | |
6 | Platform inlay |
General note on listed repair materials | |||
| Remove | ||
1 | Remove platform inlay. | ||
| |||
2 | Remove stop plugs from holes (A, B). | ||
| Install | ||
3 | Install expansion anchors for mounting tie-down rails (1). | ||
Expansion anchors are installed in bores (A). | |||
Expansion anchor to platform floor | |||
4 | Prepare adhesive for installation of tie-down rails (1, 2). | ||
The instructions in the product data and safety data sheet must be observed for this purpose. | |||
Commercially available devices/tools | |||
5 | Mask off hatched areas around the tie-down rails (1, 2). | | |
For this purpose, move tie-down rails (1, 2) to installation position and mask off adjacent areas using suitable tape. | |||
6 | Sand undersides of tie-down rails (1, 2) with enclosed sanding material. | ||
7 | Clean undersides of tie-down rails (1, 2) and bonding areas in masked off areas. | Cleaner | |
8 | Apply bonding agent to undersides of tie-down rails (1, 2). | Observe manufacturer's data for use and processing time of bonding agent. | |
9 | Retrofit lower parts of the tie-down rails (1, 2) on the platform floor. | ||
Commercially available devices/tools | |||
Bolt, lower part tie-down rail to expansion anchor/mounting plate | |||
10 | Remove tapes around tie-down rails (1, 2). | | |
| |||
11 | Install platform inlay. | ||
| |||
12 | Note down serial number. | The serial number of the tie-down rails (1, 2) is located within the tie-down rails (1, 2) at the shown positions (arrow C). | |
13 | Retrofit upper parts of the tie-down rails (1, 2) on the platform floor. | ||
Commercially available devices/tools | |||
Bolt, upper part of tie-down rail to lower part of tie-down rail | |||
Bolt, end cap to upper part of tie-down rail | |||
14 | Clean bonding surfaces for the warnings (4, 5). | Cleaner | |
15 | Bond warning (4) centrally to the inside rib of the platform paneling (3) as shown. | To do this, use rear end of the tie-down rail (7) as a dimension edge. | |
Observe dimension (b). | |||
16 | Bond warning (5) to the platform inlay (6) as shown. | To do this, bond warning (5) to the top edge (arrow D). | |
Observe dimension (C). | |||
17 | Enter special equipment with noted serial number in Vehicle Documentation (VeDoc). | Designation of corresponding special equipment: Code Y1W (load bed anchoring rails). | |
Attach noted serial number and note "Tie-down rails subsequently retrofitted with screwed cover caps on platform floor as per AN60.30-S-0030P" under field organization texts for design group 60. |
Odkazované dokumenty
- ah6000n000002p Všeobecné upozornění pro uvedené opravárenské prostředky
- an6030s002901p
- an6030s002903p
- an6030s002904p
- an6030s003002p
- ar6030s0021p Demontáž, montáž obložení valníku